The Scientific Use Of Corn Harvester

Aug 17, 2022

1. Matters that should be paid attention to when working

 

(1) Before the operation of the corn harvester, it should be smoothly combined with the working part clutch, and the throttle should be from small to large to stable rated speed before the harvest operation can be started.

 

(2) Corn harvester field operations, to regularly check the quality of cutting and crushing and stubble height, according to the situation at any time to adjust the height of the cutting platform.

 

(3) According to the number of grains thrown to the ground to check the work of the ear picking device, the amount of grain loss should not exceed 0.5% of the total amount of corn grains, when the loss of large should check the working gap between the ear picking board is correct.

 

(4) The corn harvester should be properly interrupted for 1 to 2 minutes to make the working parts run empty, so as to exclude all the corn ears, grains and other residues from the working parts, and do not allow the working parts to block. When the working part is blocked, it should be stopped in time to remove the blockage, otherwise it will lead to increased friction of the corn harvester and damage to parts.

 

⑤ When the corn harvester turns or works along the corn line when there are puddles, the cutting table should be raised to the transportation position. When there are ditches in the field, the corn harvester can only work along the direction of the ditch.

 

2. Operation test run

 

Within the first 30 hours of operation, it is recommended that the speed of the harvester be 20% ~ 25% lower than the normal speed. The normal operation speed can be carried out according to the working speed recommended by the manual. After the test run, it is necessary to thoroughly check the assembly fastening degree of each component, the correctness of assembly adjustment, the working state of electrical equipment, etc. Change the lubricating oil of all reducer and closing gearbox.

 

3. No-load test run

 

(1) Disengage the engine clutch and put the shift lever in neutral position.

 

② Start the engine and engage the clutch at low speed. When all the working parts and various mechanisms operate normally, gradually increase the engine speed until the rated speed, and then make the harvester run at the rated speed.

 

③ When running, the following checks are carried out: start the hydraulic cylinder of the hydraulic system in order to check the working condition of the hydraulic system, the sealing condition of the hydraulic pipeline and the hydraulic parts; Check the brake status of harvester (running). After EVERY 20 minutes OF operation, the engine clutch is separated to check whether the bearing is overheated, the transmission of the belt and chain, and the fastening of the connection parts. When engaging the working parts with all gears in turn, the harvester should be tested, and the conditions of each part should be paid attention to during operation. The ground to air test time of corn harvester should not be less than 3 hours, and the driving to air test time should not be less than 1 hour.

 

4. Check before the test run

 

① Check whether the installation of bearings at all parts and high-speed rotating parts on the shaft (such as stalk shredding device and middle shaft) is normal.

 

② Check the tension of V-belt and chain.

 

(3) Check whether there are tools or irrelevant items left on the harvester working parts, all the protective cover is in place.

 

(4) Check whether the fuel oil, oil and lubricating oil are in place.


Send Inquiry